Solo Cup

Overview
The lawsuit between only Cup Company (only) and Trigen-Cinergy Solutions (Trigen) arose out of an Energy run Agreement and Equipment rent that fly entered into with Trigen to construct an 11.2-megawatt electricity co-generation plant at the Owings Mills facility. alone was below the impression that by entering into this agreement, they would save at least $820,000 in aptitude costs annually, which was to be pre stipendiary by Trigen and eventually paid back by Solo over 20 grades. After Solo did analyses on the project, they observed they would actually be losing money in the first year of the contract, and took action to sever the contract. Arbitration then took place to exhibit damages to the rightful party. After extensive review of the pertinent facts in this dispute, it has come to my attention that the loss contingency is wrongly booked for Solo Cup Company. To first understand the oscilloscope of the situation, below is a summary of key events for your reference.

Timeline of Key Events
2/13/03 Solo entered into a 15 year Equipment Lease Agreement and a 20 year Energy Services Agreement with Trigen Energy Services to construct a co-generation facility.

Order your essay at Orderessay and get a 100% original and high-quality custom paper within the required time frame.



11/01/04 Trigen issued a Letter of Substantial Completion to Solo and paid out $820,000, which represented the first years energy savings prepaid by Trigen.

January 2005 Solo notified Trigen of disputes after cosmos dissatisfied that savings were not being realized.

3/21/05 Solo filed a demand for arbitration seeking recission of the Energy Services Agreement and compensatory damages plus attorneys fees, costs and interest. The claims were based on allegations of fraud, misrepresentation, promissory estoppel, unsportsmanlike enrichment, and breach of contract.

March 2005 Solo offered to settle for $3,106,972.

4/11/05 Trigen filed an answer and counterclaim seeking an award plus attorneys fees, costs, all other amounts that become due under the Energy Services...If you want to get a full essay, orderliness it on our website: Orderessay